Confirmation Hearing on 08/21/2017? Docket# 321
Debtors request the Court to set by this Motion:
(a) July 10, 2017: Record date for voting on the Plan;
(b) Four business days after entry of an order approving this Motion or as soon as reasonably practicable thereafter: Deadline for serving solicitation packages;
(c) July 21, 2017: Deadline to file motions to estimate claims;
(d) August 7, 2017: Deadline to file the Plan Supplement (as defined in the Plan);
(e) August 11, 2017: Deadline to file responses to motions to estimate claims;
(f) August 14, 2017: Voting deadline and deadline to file objections to the Plan;
(g) August 17, 2017: Deadline for hearings on motions to estimate claims;
(h) August 18, 2017: Deadline to (1) file voting tabulation, responses to objections to the Plan, and witness and exhibit lists for hearing on confirmation of the Plan and (2) serve copies of such exhibits; and
(i) August 21, 2017 at 9:30 a.m.: Confirmation hearing.