Even though the CHPP's nameplate capacity is 15.0MT ROM coal, MMC has managed to squeeze more than 100% of nameplate capacity in the past.

For example, in 2013, MMC washed 10.7MT ROM coal, using only 2 modules. I believe that would translate to about 16MT ROM of peak capacity for 3 modules.

FWIW, nameplate capacity per module in the 2013 Annual Report was calculated as follows:

850T per hour x 6000 working hrs per year = 5.1MT per module.