from Albanian newspaper - 2 June 2017
Administrative Court dismissed the lawsuit brought by some residents and land associations against the construction of hydropower plants in Valbona Valley. The Court has decided to allow the continuation of construction, and clarifies that the issue will be examined thoroughly by the administrative court.
Valbona National Park since 28 September three hydropower plants (HPP) have fastened the building permit tables, adopted on 8 September and started work.
Excavators and workers continue to work for the construction of hydropower plants with a deadline September 28 2018.
The Albanian government has adopted over the last decade three concession agreements for the construction of 14 hydroelectric power plants in Valbona river and mountain streams that make up its drainage system.
June 2, 2017 (gazeta-Shqip.com)
All of my posts are my opinion only and are not meant to be investment advice.
Unitronix Corp. to Invest $3 Million in USA Unity Coin Project • UTRX • Oct 7, 2024 7:08 AM
North Bay Resources Announces Assays up to 5 oz/ton Gold, 1.5 oz/ton Platinum, 0.5 oz/ton Palladium, and 0.5 oz/ton Rhodium at Mt. Vernon Gold Mine, Sierra County, California • NBRI • Oct 4, 2024 9:15 AM
Basanite, Inc. Appoints Ali Manav as Interim Chief Executive Officer • BASA • Oct 3, 2024 9:15 AM
Integrated Ventures Announces Launch of MedWell Facilities, LLC and Lease Agreement with Giant Fitness Clubs • INTV • Oct 3, 2024 8:45 AM
Beyond the Horizon: Innovative Drug Combinations Offer New Hope for Alzheimer's and More • NVS • Oct 3, 2024 8:45 AM
SMX and FinGo Enter Into Collaboration Mandate to Develop a Joint 'Physical to Digital' Platform Service To Enhance Natural Rubber Industry's Ability to Report on Sustainable and Ethical Supply Chains • SMX • Oct 3, 2024 7:00 AM