MMEX recent events
Project Milestones
Pecos County Refinery, Fort Stockton, Texas


Recent project milestones for the Pecos County refinery project are listed below:

•May 17, 2017: MMEX & Fort Stockton Chamber of Commerce Ambassadors Ribbon Cutting Ceremony, Opening of MMEX Office in Fort Stockton, Texas

•May 4, 2017: MMEX Executes Letter of Intent with Supplier of Refinery 50,000 BPD Crude Oil Volumes

•Apr 27, 2017: Technical Conference Status Meeting with Consultants, EPC/Environmental/Strategic Planning

•Apr 25-26, 2017: Pecos County Land site survey completed

•Apr. 18, 2017: Meetings with Investment Banks NYC, Engagement Letter pending

•Apr. 13, 2017: Environmental Firm retained to prepare and process necessary State/Federal Permits

•Apr. 12-13, 2017: Crude oil supply follow-up meetings; Draft of LOI submitted

•Mar. 25, 2017: Engineering, Procurement and Construction (EPC) Company retained

•Feb. 27, 2017: Strategic Consultant and Industry Advisor retained

•Feb. 20, 2017: Pecos County Land Purchase and Sale Agreement
Executed (500 acres)

•Feb. 15, 2017: Public Relations Firm retained

•Feb. 14, 2017: Pre-permit meeting held with Texas Commission on Environmental Quality (TCEQ