The Merrill Crowe was never the answer. It was part of the puzzle. The whole mining process is one giant system and so the system is only as fast as the slowest part. If you only have on front loader to pile dirt on the heap then that's as fast as you can move even if you have a massive M/C.

SO
Blast>Scoop>Jawcrush/sift for ideal size for heap so no channeling>Spray cyanide>recovery pond>MC>Smelt