Re: Tx Girl post# 46532

Wednesday, 03/22/2017 2:48:52 PM

Wednesday, March 22, 2017 2:48:52 PM

Post# of 58418

"However, to give him the benefit of the doubt a can order and ingredients should be placed by next week if that's where he is at in the process. He may not hit the April 15 date, but I can let that go, as long as an order is in place, because delays can happen."

No. To have hit the April 15th target for having possession of new inventory, Adrian had to order production components last week.

There is a 14 to 30 day lead time on receiving empty cans and energy drink components after they are ordered.

That is followed by another 14 to 30 day lead time on the co-packers using the components to produce new inventory.

This is NOT my opinion or speculation. These lead times are clearly spelled out in the corporate filings. Go read them for yourself.

There will be no new inventory on April 15th.