KERR MINES COMPLETES DEWATERING AT COPPERSTONE AND BEGINS NEXT PHASE TOWARDS RE-START OF PRODUCTION

TORONTO, March 2, 2017 /CNW/ - Kerr Mines Inc. ("Kerr" or the "Company") (TSX:KER) today announced that it has successfully completed its de-watering program at its flagship Copperstone mine in Arizona and has started the next phase of its plan to define and expand current resources, and establish a new production plan.
"We continue to make significant progress with our turnaround strategy and completed the dewatering program on time and budget," said Chris Hopkins, Interim President and CEO. "With mine access now reestablished, we are well positioned to aggressively pursue our updated resource modelling, mine plan and production restart program."

Completion of the dewatering program has allowed for underground rehabilitation work to provide access for underground activities consisting of diamond drilling (expansion and definition) and additional mine development. The Company intends to pursue concurrent underground development and exploration programs to define and expand current resources, and establish a new production plan for underground mining at Copperstone.

Existing underground development allows for access to initial development and diamond drilling of the C, B and A Zones. The C, B and A Zones have not yet been developed or drilled from underground, however they have been drilled extensively from surface and open pit stations. All of the above zones were mined from open pit yielding approximately 500,000 ounces to a depth of slightly over 100 meters or 4,700 ounces per vertical meter. The dewatering program and subsequent rehabilitation at Copperstone has been completed in order to begin this next phase of activity.

As previously announced, the Company engaged JDS Energy and Mining Inc. ("JDS") to provide engineering and economic evaluation consulting services in support of the Company's Copperstone mine. JDS, together with Kirkham Geosystems, has retrieved and converted all historic data to a geological model that will be used as a basis for the definition drilling and development program expected to begin in Q2 2017.



http://kerrmines.com/release/?id=122645