Full Mill 2000 tons per day. Full Leach, CIL.
Crush Grind 200 Mesh,
43 million
Open Pit and Shovel R16, Truck.
6 million
Housing, offices Air strip dock and port facility.
5.5
Things we forgot
6.5
= 61 million.
I think they have an estimate of this in their news announcements of the last few months. I don't know what their figure was but they were dicussing what the cost
saving of going from straight leach from float leach would
be in throughput. I would dispute that concept but they did discuss it.
EC<:-}
EC<:-} Wildcat Res. Ltd.
Avant Technologies Equipping AI-Managed Data Center with High Performance Computing Systems • AVAI • May 10, 2024 8:00 AM
VAYK Discloses Strategic Conversation on Potential Acquisition of $4 Million Home Service Business • VAYK • May 9, 2024 9:00 AM
Bantec's Howco Awarded $4.19 Million Dollar U.S. Department of Defense Contract • BANT • May 8, 2024 10:00 AM
Element79 Gold Corp Successfully Closes Maverick Springs Option Agreement • ELEM • May 8, 2024 9:05 AM
Kona Gold Beverages, Inc. Achieves April Revenues Exceeding $586,000 • KGKG • May 8, 2024 8:30 AM
Epazz plans to spin off Galaxy Batteries Inc. • EPAZ • May 8, 2024 7:05 AM