Wednesday, December 23, 2015 3:30:41 PM
They started grading on 1 October, which should take 3 days for this small size plot. It's tiny in the construction world
The admin building was delivered July 31 to the builder.
This project is a very simple one, especially with a prefab building. I'm in industrial and commercial construction. There's only 2 reasons that I can deduce that this project is still in the concrete phase .
1. A lack of urgency to be completed, a no need to rush mindset, which the men swinging the hammers get from the ownership and company management
2. The builder has a hard time collecting funds. About 1 out of 10 jobs I've run, the client falls behind in getting us a check. No check, no manpower.
There's no reason this shouldn't be a viable building by now.
NanoViricides Reports that the Phase I NV-387 Clinical Trial is Completed Successfully and Data Lock is Expected Soon • NNVC • May 2, 2024 10:07 AM
ILUS Files Form 10-K and Provides Shareholder Update • ILUS • May 2, 2024 8:52 AM
Avant Technologies Names New CEO Following Acquisition of Healthcare Technology and Data Integration Firm • AVAI • May 2, 2024 8:00 AM
Bantec Engaged in a Letter of Intent to Acquire a Small New Jersey Based Manufacturing Company • BANT • May 1, 2024 10:00 AM
Cannabix Technologies to Deliver Breath Logix Alcohol Screening Device to Australia • BLO • Apr 30, 2024 8:53 AM
Hydromer, Inc. Reports Preliminary Unaudited Financial Results for First Quarter 2024 • HYDI • Apr 29, 2024 9:10 AM