Try again... two things that stand out in the PEA NR.........

In the PEA, ERCOSPLAN recommends additional flotation testwork and an additional solution cavern to produce brine for further evaporation testwork, to facilitate a Feasibility Study evaluating the potential to concurrently extract both MOP and SOP from the same brine field. Additional studies currently in progress including an Aquifer Stress Test (AST) and Solution Well #3 (SW3) will provide valuable information for this evaluation. The AST is intended to confirm the viability of Allana's long-term water supply by pumping water at greater than planned production rates from one of the projected water supply fields for an extended period, now complete. SW3 is a production-scale solution well currently in operation to supplement experience from the pilot-scale solution well work from the Feasibility Study, and to produce brines from the Kainitite horizon through to the Sylvinite horizon to optimize solution mining configurations for the Project.

and

The SOP operation provides an option, if a second feasibility study incorporating SOP proves positive, to complement or expand upon the MOP operation and various production scenarios will be under evaluation.
Join InvestorsHub

Join the InvestorsHub Community

Register for free to join our community of investors and share your ideas. You will also get access to streaming quotes, interactive charts, trades, portfolio, live options flow and more tools.