I hope that Allana will follow the modular construction plan and start small scale production next year. That would send the SP over a buck in a hart beat.
(see below, emphasis by me)
During the FEED engineering phase AMEC will also undertake the following:
-- Prepare the Project Management Plan (PMP) including a Work Breakdown
Schedule (WBS) and definition of supply and construction scopes and
packages.
-- Develop a resource-loaded Level 3 project engineering,
procurement/contracting and construction schedule, with detailed
estimates of construction staffing requirements
-- Prepare principal design documents such as design criteria, flow sheets,
P&IDs, single line diagrams, site plans, and general arrangements, in
preparation for final detailed engineering and construction documentation
-- Complete civil, concrete and steel materials take-offs (MTOs) based on 3D
modeling
-- Complete trade-off and optimization studies related to certain process
components, modularization, power supply, materials movement and layout
options
-- Develop the procurement and construction contracting plan, completing the
list of qualified prospective suppliers and contractors