Cumberland Announces Increase in Open Pit Potential at Meadowbank
Thursday May 29, 12:57 pm ET


VANCOUVER, BRITISH COLUMBIA--CUMBERLAND RESOURCES LTD. (CBD-TSX) announces that ongoing open pit mining studies by international engineering firm AMEC on the Vault resource model(1) (see news release NR03-04) have expanded the potential pit resource and potentially eliminated or deferred the need for underground mining at the Vault deposit, one of five gold deposits at the Company's 100% owned Meadowbank gold project, located 70 kilometres north of Baker Lake, Nunavut.
A preliminary assessment(2) of the project was completed in early 2002. The study indicated the five gold deposits comprising the Meadowbank project could support a production rate of approximately 250,000 ounces per year at an estimated cash cost of US$168 per ounce over an eight year mine life, with 85% of production from open pit designs including a shallow open pit at the Vault deposit. A component of the remaining 15% of production was scheduled from underground mine designs at the Vault deposit.

A feasibility study on the Meadowbank project was initiated in October 2002. The feasibility study will now consider the option of operating the Meadowbank project solely on an open pit basis for 10 years, potentially eliminating or deferring the capital and higher cost associated with underground mining.

Vault Preliminary Open Pit Designs

The revised preliminary open pit designs at the Vault deposit were developed using the same operating cost estimates used in the preliminary assessment(2) together with results from 2002 geotechnical drill programs, improved metallurgical recoveries (see news release NR02-21) and enhanced resources(1) (see news release NR03-04) resulting from 2002 definition drill programs. Drilling to improve resource definition continues at the Vault deposit with over 86 new holes completed in the past 60 days. Results will be announced shortly.

Vault Revised Preliminary Pit Designs - May 2003 (US$325/oz)
--------------------------------------------------------------
Category Tonnes Grade (g/t) Ounces Gold
--------------------------------------------------------------
Measured and Indicated 4,100,000 3.59 473,000
--------------------------------------------------------------
Inferred 3,100,000 3.63 362,000
--------------------------------------------------------------

Note: Revised preliminary designs do not include provision for mining
dilution and generate a waste to ore strip ratio of 9:1. Mineral
resources which are not reserves do not have demonstrated economic
viability. A cut-off grade of 1.85 g/t was used.

These results compare very favorably to previous preliminary pit designs
reported in the preliminary assessment from early 2002:

Vault Preliminary Pit Designs - January 2002 (US$325/oz)
--------------------------------------------------------------
Category Tonnes Grade (g/t) Ounces Gold
--------------------------------------------------------------
Inferred 1,659,000 3.74 138,000
--------------------------------------------------------------


Note: Preliminary pit designs include provisions for anticipated mining dilution and generate a strip ratio of 5.6:1.

The preliminary assessment also included an underground component at the Vault deposit comprising 1,271,000 tonnes of inferred resource grading 5.32 g/t (217,000 ounces).

Meadowbank Gold Project

Mining studies are part of Cumberland's $10.5 million 2003 program at Meadowbank, which includes ongoing feasibility level engineering, drilling programs and environmental impact studies.

Meadowbank is host to the third largest undeveloped gold resource in Canada with six closely spaced, near surface, gold deposits totaling:

Meadowbank Project - Resources (Q1/2003)(3)
------------------------------------------------------------------------
Measured and Indicated 12,309,000 t grading 5.00 g/t 1,979,000 oz. gold
------------------------------------------------------------------------
Inferred 9,290,000 t grading 4.20 g/t 1,255,000 oz. gold
------------------------------------------------------------------------


Cumberland is well financed with approximately $17 million in its treasury. Cumberland holds interests in two of the largest undeveloped gold projects in Canada: the Meadowbank (100%) and Meliadine West (22% carried) projects in Nunavut. The Company is also exploring for diamonds at the Meliadine East (50%) project in Nunavut.

CUMBERLAND RESOURCES LTD.

Kerry M. Curtis, B.Sc., P.Geo., President and CEO

(1) Vault resource model: James McCrea, P.Geo., Manager, Mineral Resources is Cumberland's Qualified Person for the resource modeling. Resource classification conforms to CIM Standards on Mineral Resources and Reserves (August 2000).

(2) Cautionary Note: The preliminary assessment completed in January 2002 is preliminary in nature, included inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that the preliminary assessment will be realized. The production forecast used in the Preliminary Assessment included approximately 5.9 million tonnes of Inferred Mineral Resource, or 41% of the total forecast. In compliance with National Instrument 43-101, the Company issued a Technical Report which is available at www.sedar.com for review.

(3) First quarter 2003 resource estimates and classification are in accordance with National Instrument 43-101 and conform to CIM Standards on Mineral Resources and Reserves (August 2000).

This document contains certain forward looking statements which involve known and unknown risks, delays, and uncertainties not under the Corporation's control which may cause actual results, performance or achievements of the Corporation to be materially different from the results, performance or expectations implied by these forward looking statements.


--------------------------------------------------------------------------------
Contact:

Cumberland Resources Ltd.
Kerry Curtis
President and CEO
Phone: (604) 608-2557
Fax: (604) 608-2559
or
Cumberland Resources Ltd.
Joyce Musial
Manager Investor Relations
Phone: (604) 608-2557
Fax: (604) 608-2559
Email: info@cumberlandresources.com
Website: www.cumberlandresources.com




Ed