Watts Bar 2 nears completion

Jim Matheny, WBIR 7:30 p.m. EDT July 24, 2014

(WBIR - Rhea County) The parts are in place and ready to assemble the new reactor at the TVA Watts Bar nuclear power plant.

TVA expects assembly of the Watts Bar 2 reactor to begin in the next few days. The assembly is a combination of extremely heavy equipment that requires delicate surgical precision.

WBIR toured the construction site and vessel that will house the reactor on Thursday morning. TVA says 90 percent of total construction of the project is now complete.

http://www.wbir.com/story/news/local/2014/07/24/watts-bar-2-nuclear-reactor-assemble/13129195/