U.S. SILVER & GOLD INC. MANAGEMENT’S DISCUSSION AND ANALYSIS
FOR THE THIRD QUARTER ENDED SEPTEMBER 30, 2012

DATED NOVEMBER 13, 2012


https://www.otciq.com/otciq/ajax/showFinancialReportById.pdf?id=94335

Drumlummon Gold Mine, Marysville, MT -

some early mine work and old pictures by prev. contracted out work -

• 2000’ of 13’x15’ decline driven
• 3000’ of 12’x12’ decline driven
• 1500’ of 10’x11’ lateral drifts driven
• 1500’ of ore development drift driven
• Bean holes and timber raises driven on ore
• Shrink stope and long hole stope ore body
• 8+ Diamond Drill stations cut
• Prep, cut, and timber 14’x15’ portal
• Remove and rebed 1100’ of rail.
• Relay ties, 1100’ of rail and ballis
• Re-timber 250’ of 3 compartment shaft
• Dig and install several thousand feet of 6” pipe on surface
• Raise and re-post 50 sets of timber through old workings
• 100+ employees on job













http://investorshub.advfn.com/boards/read_msg.aspx?message_id=81485442


My opinions are my own and and DD I post should be confirmed as unbiased

Volume:
Day Range:
Bid:
Ask:
Last Trade Time:
Total Trades:
  • 1D
  • 1M
  • 3M
  • 6M
  • 1Y
  • 5Y
Recent USA News