Saturday, October 28, 2017 10:02:32 AM
Final EPA Permit Grant: Mid December 2017
Stage 1 Construction Financing: Mid January 2018
Stage 1 Production Start: 3Q 2018
Stage 1 Cu Recovery Rates Validation: 1Q 2019
After that, the best we can surmise is the schedule defined in the FS with cash flows shown in table below.