Right on Schedule
The two starter buildings have arrived at the Marapharm property located in Las Vegas, Nevada. Site preparation is underway. Forms and slab pour and cure time is slated to be January 16, 2017. The building erection crew is slated to begin January 17, 2017. Interior prep and finishing for grow ready is to commence January 28, 2017. Fencing, security and signage is projected for completion February 20, 2017. Numerous construction items and interior furnishings, equipment and preparations to go to March 30, 2017 and growing, cultivation and processing for 3 licensed facilities commences April, 2017. Delivery of pre-sold cannabis after curing, testing and packaging projected to be within 3 months of the initial harvest.