Re: BigBaboon post# 351

Tuesday, 02/02/2016 10:12:30 AM

Tuesday, February 02, 2016 10:12:30 AM

Post# of 1228
Mr Primate:

Public information available to all from the QEGY press release, a partial copy and paste:

"Jul 29, 2015) - Bakken energy processing developer Quantum Energy, Inc. (OTC PINK: QEGY), in conjunction with its joint venture partner, Native Son Refining, LLC, announced the filing of a minor source air quality construction permit application today with the North Dakota Health Department, Division of Air Quality. The permit application is to construct a 40,000 barrel per day crude processing facility on land Quantum has under option in the Berthold area."

1. Aug 29
2. Sept 29
3. October 29
4. Nov 29
5. Dec 29
6. Jan 29

Seems the 6 month permit review period has run its course. I have subscribed to the North Dakota permit site, receive notices about various projects, waiting for their announcement.

What is the status of the construction permit?