4/15/08
(1) Furling system stand off, 4”x 4”x ¼” steel tubing, 26” long
24 cuts at 3 minutes per cut= 72 minutes
24 holes at 2 min/hole= 48 minutes (tower mount holes)
4 holes x 24 pieces x 1 hole/min= 96 minutes (rail mount plates)
(2) Strut bar to brace tower top leg 4”x 4”x ¼” steel angle
4 pieces x 2 holes/piece x 2 min/hole= 16minutes drilling
(3) Tower top leg 4”x 4”x ¼” steel tubing, 8’ long
Joint plate weld, 16” x 4 x 1”/min= 64 minutes weld time
Clamp plate holes 4 holes x 3 min/hole= 12 min
(4) Tubing supports, 4”x 4”x ½” steel angle, 4” long, same as tower pieces
24 cuts at 3 min/cut= 72 minutes
12” weld x 24 pieces x 1”/min= 288 min
(5) Garage channel mount plate 2” x ¼” x 8’ long (note 1)
12 pieces x 2 holes x 1 min/hole= 24 min
(6) Garage channel mount plate 2” x ¼” x 10’ long (note 1)
18 pieces x 2 holes x 1 min/hole= 36 min
(7) Bearing mount plates 4” x ½” x 8” long, see detail drawing
18 cuts x 2 minutes /cut= 36 minutes
18 pieces x 12” weld x 1”/min= 216 minutes
18 pieces x 4 holes x 2 min/hole= 144 minutes
18 pieces x 1 hole and slot cut x 4 min/slot= 72 minutes
(8) End clamp plate 4”x 8” x Y” thick, same as tower pieces
16 cuts at 3 min each= 48 minutes
16 plates x 2 holes/plate x 2 min/hole= 96 minutes
(9) Panel Cross Rails 1 ½” x 1/8”, 9’4” long,
48 cuts to 9’4” x 2 min/cut= 96 minutes
9” of weld per rail x 48 rails x 1”/min= 432 minutes
28 holes/panel x 3 panels x 1 min/hole= 84 minutes
(10) Panel Side Rails 2” x ¼” steel angle, 5’ long
15 cuts x 2 min/cut= 30 minutes
20 axles/panel x 4 holes x 3 panels x 1 hole/minute= 240 minutes
4 axles/panel x 4 holes x 3 panels x 1 hole/min= 48 minutes
(11) Chain end plate, #35 chain
12 pieces 4 holes/plate x 1 min/hole= 48 minutes
(12) Furling panel counter weight, 6 each of 6” pipe, 24” long, with chain attachment bar and hole to fill pipe.
6 cuts x 4 min/cut= 24 minutes to cut pipe
12 cuts x 3 min/cut= 48 minutes to cut top and bottom plate
12 cuts x 2 min/cut= 24 minutes for chain attachment plates
6 holes x 4 min/hole= 24 minutes drilling fill holes
12 holes x 3 min/hole= 24 minutes drilling chain attachment holes
12 welds x 19” x 1”/min= 228 minutes end plate welds
12 welds x 15” x 1”/min= 180 minutes chain attachment plates
Note 1: Need detail of garage rail mounting to determine holes to be drilled in this rail and time in shop fabrication.
Shop Fabrication Time by operation
Cutting Drilling Welding
(1) 72 144
(2) 16
(3) 12 64
(4) 72 288
(5) 24
(6) 36
(7) 36 216 216
(8) 48 96
(9) 96 84 432
(10) 30 288
(11) 48
(12) 72 48 408
426 1012 1408
2846 minutes of shop fabrication time on the furling system
47 hours of shop fabrication time
Does not include vertical webs for furling panels and some drilling for garage rail mounting.
Recent MMMW News
- Form NT 10-K/A - Notification of inability to timely file Form 10-K 405, 10-K, 10-KSB 405, 10-KSB, 10-KT, or 10-KT405: [Amend] • Edgar (US Regulatory) • 07/30/2024 09:25:34 PM
- Form NT 10-K - Notification of inability to timely file Form 10-K 405, 10-K, 10-KSB 405, 10-KSB, 10-KT, or 10-KT405 • Edgar (US Regulatory) • 07/30/2024 08:39:03 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 07/26/2024 08:36:10 PM
- Form DEFA14A - Additional definitive proxy soliciting materials and Rule 14(a)(12) material • Edgar (US Regulatory) • 07/26/2024 07:32:09 PM
- Mass Megawatts Announces $220,500 Debt Cancellation Agreement to Improve Financing and Sales of a New Product to be Announced on July 11 • InvestorsHub NewsWire • 06/28/2024 11:30:00 AM
- Form 8-K - Current report • Edgar (US Regulatory) • 05/15/2024 03:44:27 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 05/08/2024 12:10:37 PM
- Mass Megawatts Announces Several New Product Lines with Lowest and Competitive Prices as a Source of Generating Revenue in this Fiscal Quarter and to Help Market our Patent Pending Solar Tracker • InvestorsHub NewsWire • 02/22/2024 01:00:00 PM
- Form DEFA14A - Additional definitive proxy soliciting materials and Rule 14(a)(12) material • Edgar (US Regulatory) • 02/12/2024 11:01:42 AM
- Form DEF 14A - Other definitive proxy statements • Edgar (US Regulatory) • 02/09/2024 06:02:22 PM
- Form PRE 14A - Other preliminary proxy statements • Edgar (US Regulatory) • 01/26/2024 10:03:45 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 01/26/2024 09:20:13 PM
- Form 10-Q - Quarterly report [Sections 13 or 15(d)] • Edgar (US Regulatory) • 12/06/2023 05:30:56 PM
- Mass Megawatts Announces LOWEST PRICE GUARANTEE on Solar Project Sales and Further Cost Reductions Using our Patent Pending Technologies • InvestorsHub NewsWire • 11/28/2023 01:00:00 PM
VHAI - Vocodia Partners with Leading Political Super PACs to Revolutionize Fundraising Efforts • VHAI • Sep 19, 2024 11:48 AM
Dear Cashmere Group Holding Co. AKA Swifty Global Signs Binding Letter of Intent to be Acquired by Signing Day Sports • DRCR • Sep 19, 2024 10:26 AM
HealthLynked Launches Virtual Urgent Care Through Partnership with Lyric Health. • HLYK • Sep 19, 2024 8:00 AM
Element79 Gold Corp. Appoints Kevin Arias as Advisor to the Board of Directors, Strengthening Strategic Leadership • ELMGF • Sep 18, 2024 10:29 AM
Mawson Finland Limited Further Expands the Known Mineralized Zones at Rajapalot: Palokas step-out drills 7 metres @ 9.1 g/t gold & 706 ppm cobalt • MFL • Sep 17, 2024 9:02 AM
PickleJar Announces Integration With OptCulture to Deliver Holistic Fan Experiences at Venue Point of Sale • PKLE • Sep 17, 2024 8:00 AM