I communicated with CAM this morning. Read bottom to top.:
Do you have any clue if we are waiting on a permit to be authorized? There was an extended due date of today for the permit that covers several things, including expansion of holding areas and increases in mill.
On Mon, Mar 15, 2010 at 9:21 AM, Charles Moskowitz <charles.moskowitz@gmail.com> wrote:
I've called David and left message..I'll get back to you ASAP...CAM
On Mon, Mar 15, 2010 at 8:52 AM, Brian Rubick <brian.rubick@gmail.com> wrote:
Hey Charles,
I hope your mouth is feeling better and the pain has subsided.
I know you are getting bombarded with emails and phone calls, but I was hoping you could give us a quick update on the mill restart. We saw that ore was being crushed and the 2 shifts for 2 days should have easily been satisfied. Are there further delays?
Thanks,
Brian