InvestorsHub Logo
Followers 20
Posts 7168
Boards Moderated 0
Alias Born 03/02/2013

Re: None

Saturday, 08/05/2017 5:56:17 PM

Saturday, August 05, 2017 5:56:17 PM

Post# of 14330

Burnstone is located in the South Rand Goldfield of the Witwatersrand Basin near the town of Balfour, approximately 75km east of Johannesburg in the Mpumalanga province of South Africa.

Sibanye acquired the Burnstone assets in April 2014, comprising two shaft complexes, namely the surface portal and mechanised vehicle access decline and the vertical shaft (shaft bottom at 495m below surface), as well as a 125,000tpm gold processing plant, the tailings storage facility and surface infrastructure to support a producing operation, albeit with areas still to be constructed.

Burnstone had previously produced approximately 38,000oz of gold before being placed on care and maintenance in mid-2012.

The Burnstone project feasibility study was approved by the Board for project execution in November 2015. The project is planned with a five-year build-up to steady-state production by 2021, then averaging 120,000oz annually for nine years till the end of 2029. Thereafter a 10-year period of decreasing but profitable production supports an initial 26-year life-of-mine plan, yielding 2.05Moz of gold production. This initial LoM plan was limited to approximately 60% of the total Burnstone resource as the mine design and schedule in the feasibility study were limited to mineable reserves within a 3km radius of the shaft infrastructure.

First gold production is planned in the second half of 2018 when there is sufficient on-reef development stockpiled (2.5 years) to start up the metallurgical plant, albeit at a reduced milling capacity. The full production run rate is planned to be achieved in 2021 and the total LoM project capital is estimated at R1,852 million (in 2015 terms).

In 2015, concurrent with completing the feasibility study, R272 million was spent on completing the mine-dewatering and permanent pumping infrastructure, re-aligning the shaft steelwork for rock-hoisting, and completing approximately 2km of development to commence accessing the orebody. The development was completed utilising the existing mechanised development machines which were first refurbished before being put back into production. Three development fleets of equipment were in production by year end.

In 2016, R531 million was spent in the first full year of the feasibility study build-up where the expenditure provided for:
·4,950m of development. In the fourth quarter, with all development fleets in production, 1,915m of the planned 2,100m was produced and the team’s performance has steadily improved

·mine infrastructure running costs

·planned project capital infrastructure

·procurement of additional mechanised mining fleets and ancillary support vehicles

The budget for 2017 has been revised to R400 million – compared to an initial budget of R672 million – to deliver 6,000m of access development (this is a reduction from the feasibility study’s 8,300m of access development) and to run the mine in support of this revised plan and defer certain project infrastructure.


https://www.sec.gov/Archives/edgar/data/1561694/000155837017002504/sbgl-20161231x20f.htm

Table of Contents

As a result of the recent strength in the rand and its impact on operating margins for the gold industry, organic project capital expenditure has been reviewed. This includes a review of the planned 2017 capital profile at the UG2 project at Rustenburg, the Burnstone project and the West Rand Tailings Retreatment Project (WRTRP). Certain projects may be deferred or placed on care and maintenance until commodity prices sustainably improve and/or exchange rate volatility has subsided.



Burnstone going on care and maintenance yet again, hmmm...?

Join the InvestorsHub Community

Register for free to join our community of investors and share your ideas. You will also get access to streaming quotes, interactive charts, trades, portfolio, live options flow and more tools.