Nothing but lies – Best of Jack Bal

News release 4 December 2013
“Construction of the tailings pond will begin before the end of the year.”

News release 18 March 2014
- “Exploration and development drifting and drilling will occur to define the extent of the high grade zone plus prepare development workings. As the development workings proceed, ore will be produced.”
- “The Bishop Mill is expected to be functional in June 2014.”

News release 24 September 2014
“The pond has been excavated and installation of the liner will commence within the next two weeks and will take an additional two weeks to complete. A new assay lab has been installed and upgrades to the Mill are ongoing. The Company anticipates being operational at the Bishop Mill with stock piled ore prior to year end.”

News release 22 October 2014
“International Lining Technology will commence installation of the pond liner in one week.”

Interview October 2014
- “We are drifting to a zone that was intersected by a high grade intersection of over 5 ounces gold per ton. We have an option to ship directly to Newmont to create cash-flow before the mill is fully operational.”
- “We will need $400k to complete both Mill and Mine.”
- “The company is run very efficiently. We realize pro¬fit is the most important thing for a junior company.”
- “We are submitting a new exploration permit shortly.” (related to Silver Hart)

News release 11 March 2015
“It is anticipated that the Bishop Mill will be fully operational in the next sixty (60) days.”

News release 25 June 2015
“Final permitting is progressing at the Bishop Mill and the Company expects completion shortly.”